project description
Emergency mitigation measures to ensure the safe operation of the overpass on Oleksandra Ekster Street over the high-speed tram railway tracks, Kyiv.
Consequence (Responsibility) Class: CC3 – significant consequences
Implementation period: 2025–2026
General data:
Year of construction: 1999;
Structure length: 63.24 m;
Clearance (gauge): 24 + 2.4 + 1.8 + 6 m;
Minimum under-bridge clearance: 5.24 m.
Works:
The following works were carried out in 2025:
Repair and strengthening of concrete surfaces of the abutments — 396m²;
Replacement of rubber bearing pads of the superstructure — 50 units;
Dismantling of existing metal and concrete stairways.
The following works are scheduled to be carried out in 2026:
Repair of superstructure beams — 543 m²;
Repair of retaining walls — 214 m²;
Construction of stairways on the embankment and beneath the superstructure;
Installation of a new bridge deck;
Installation of a drainage system — 215 m;
Repair of lighting poles.
project status
In progress.
project description
Services for the implementation of emergency mitigation measures to ensure the safe operation of Overpass No. 2 on Zhilyanska Street, Kyiv.
Consequence (Responsibility) Class: CC3 – significant consequences
Implementation period: 2025–2026
General data:
Year of construction: 1978;
Structure length: 147.81 m;
Clearance (gauge): 14 + 1.33 + 0.87 m.
Works:
The following works were carried out in 2025:
Repair of concrete surfaces of pier crossbeams and their anti-corrosion protection – 438 m²;
Strengthening of pier columns and their anti-corrosion protection-173 m².
The following works are scheduled to be carried out in 2026:
Repair of expansion joints over the abutments and intermediate piers.
project status
In progress.
project description
Major Overhaul of the Overpass near Osokorky Metro Station on Mykola Bazhan Avenue in Kyiv
Consequence (responsibility) class: CC3 – significant consequences.
Start of works: July 2025
Completion of works: December 2026
General information:
Length of the overpass: 153.69 m;
Total area of the roadway: 16,339 m²;
Total area of sidewalks: 4,489 m²;
Total area of bicycle paths: 1,288 m².
The following works will be carried out on the site:
Dismantling of the existing overpass structures;
Construction of new piers and span structures;
Construction of the roadway structures;
Repair of the approaches to the overpass;
Construction of sidewalks and bicycle paths.
The work is carried out using modern materials and the latest advanced technologies.
project status
In progress.
project description
Emergency Repair Measures for Piers No. 1 and No. 4 of the Overpass at the Intersection of Mykhaila Boichuka Street and the Kyiv-Demiivskyi Railway Station
Description of the facility:
Year of construction: 1991;
Total length of the overpass: 223.3 m;
Cross-sectional dimension G: 24 + 2×3.47 m;
Consequence (responsibility) class: CC3;
Total repair area of the piers: 1177 m².
The following works will be carried out on the site:
Repair of expansion joints above piers No. 1, 4, 7, and 10;
Dismantling of sidewalk blocks along the entire length of the structure;
Restoration and reinforcement of concrete surfaces of piers No. 1, 4, 7, and 10;
Installation of safety barriers on the roadway until the start of major repairs.
Start of works: May 2025
Completion of works: December 2026
project status
In progress.
project description
Major repair of the overpass at the intersection of Lugova street and Bohatyrska street, Kyiv.
Consequence class (responsibility) CC3 – significant consequences.
Execution term — 2024-2025.
General Information:
Overpass length — 84.93 m;
Retaining wall repair area — 815 m2;
Total roadway area — 6,792 m2;
Total sidewalk area — 1,769 m2;
Total bicycle lane area — 2,535 m2.
Works to be performed:
replacement and repair of overpass structures;
repair of concrete surfaces of retaining walls;
repair of overpass approaches;
construction of sidewalks and bicycle lanes.
The works are carried out using modern materials and the latest advanced technologies.
project status
Completed.
project description
Major repair of the bridge with approaches (108.95 m) on public National importance motor road Odesa-Voznesensk-Novyi Buh, Mykolaiv region.
Consequence class (responsibility) CC3 – significant consequences.
Execution term — 2024.
General information:
Road category — II;
Bridge length – 108,95 m;
Bridge clearance G-9,5+1,8*2;
Geometric scheme — 6*18 m;
Lane width — 3,75 m.
project status
Completed.
project description
Major repair of the bridge with approaches (36.8 m) on public National importance motor road Odesa-Voznesensk-Novyi Buh, Mykolaiv region.
Consequence class (responsibility) CC2 – medium consequences.
Execution term — 2024.
General information:
Road category — II;
Bridge length – 34.9 (36.8) m;
Bridge clearance G-8.5+1.8*2;
Geometric scheme — 311.36 (312) m;
Lane width — 3.75 m.
project status
Completed.
project description
Major repair of the bridge crossing over the Irpin river on the state road Kyiv-Ivankiv-Ovruch, Kyiv region.
Consequence class (responsibility level): CC3 – significant consequences.
Completion timeframe: 2023–2024.
General specifications:
Road category: II;
Bridge length: 155.95 m;
Bridge width: 13.99 m;
Number of traffic lanes: 2;
Span structure layout: 18 + 16.76 + 6×18 + 12 m;
Dimensions: 9.5 + 2.5 + 0.75 m;
Temporary loads: A-15, NK-100.
Scope of work:
dismantling of damaged structures of the existing bridge;
construction of monolithic foundations for supports on driven reinforced concrete piles;
installation of prefabricated-monolithic supports;
assembly of I-shaped pre-stressed girders for span structures;
construction of a monolithic reinforced concrete slab for the roadway and sidewalks;
installation of closed-type expansion joints;
application of asphalt concrete pavement;
installation of drainage and water disposal systems for the roadway;
installation of galvanized pedestrian and barrier railings;
construction of connection elements between the bridge and approaches;
anti-corrosion protection of steel and concrete surfaces.
project status
Completed.
project description
Major repair of the overpass at the intersection of Novokonstantynivska street with Olena Teliha street and Stepan Bandera avenue, Kyiv
Consequence class (responsibility level): CC3 – significant consequences.
Completion timeframe: 2023.
General specifications:
Bridge length: 123.4 m;
Dimensions: 18.78 m + 2×0.75 m;
Retaining wall repair area: 2,920 m2;
Pier repair area: 447 m2.
Scope of work:
repair and anti-corrosion protection of retaining walls;
repair and anti-corrosion protection of piers;
installation of longitudinal drainage systems.
project status
Completed.
project description
Major repair of the bridge on the state road Kazanka–Snigurivka, Mykolaiv region.
Consequence class (responsibility level): CC3 – significant consequences.
Completion timeframe: 2023.
General specifications:
Road category: III;
Bridge length: 49.11 m;
Span structure layout: 15 + 18 + 15 m;
Number of traffic lanes: 2;
Bridge width: 10.77 m;
Dimensions: 8.0 + 2×0.75 m;
Temporary loads: A-15, NK-100.
Scope of work:
dismantling of damaged structures of the existing bridge;
construction of monolithic foundations for supports on driven reinforced concrete piles;
installation of prefabricated-monolithic supports;
assembly of I-shaped pre-stressed girders for span structures;
construction of a monolithic reinforced concrete slab for the roadway and sidewalks;
installation of closed-type expansion joints;
application of spray-applied waterproofing;
installation of asphalt concrete pavement;
installation of drainage and water disposal systems for the roadway;
installation of galvanized pedestrian and barrier railings;
construction of connection elements between the bridge and approaches;
anti-corrosion protection of steel and concrete surfaces.
project status
Completed.
project description
Major repair of the bridge crossing over the Irpin river on the state road Kyiv-Fastiv-Bila Tserkva-Tarascha-Zvenyhorodka, Kyiv region
Consequence class (responsibility level): CC3 – significant.
consequences. Completion timeframe: 2022–2023.
General specifications:
Road category: II;
Bridge length: 52.3 m;
Span structure layout: 18 + 21 + 18 m;
Number of traffic lanes: 2;
Bridge width: 12.79 m;
Dimensions: 9.0 + 0.75 + 1.8 m;
Temporary loads: A-15, NK-100.
Scope of work:
dismantling of damaged structures of the existing bridge;
construction of monolithic foundations for supports on driven reinforced concrete piles;
installation of prefabricated-monolithic supports;
assembly of I-shaped pre-stressed girders for span structures;
construction of a monolithic reinforced concrete slab for the roadway and sidewalks;
installation of closed-type expansion joints;
application of spray-applied waterproofing;
installation of asphalt concrete pavement;
installation of drainage and water disposal systems for the roadway;
installation of galvanized pedestrian and barrier railings;
construction of connection elements between the bridge and approaches;
anti-corrosion protection of steel and concrete surfaces.
project status
Completed.
project description
Major repair of the bridge over the Desna river on the state road Sosnytsia — Shapovalivka, Chernihiv region.
Consequence class (responsibility level): CC2 – medium consequences.
Completion timeframe: 2022–2024.
General specifications:
Road category: III;
Bridge length: 304.70 m;
Span structure layout: 18 + 2×24 + 42 + 63 + 42 + 3×24 + 18 m;
Number of traffic lanes: 2;
Bridge width: 12.90 m;
Dimensions: 10.0 + 2×1.0 m;
Temporary loads: A-11, NK-80.
Scope of work:
dismantling of damaged structures of the existing bridge spans 7–11;
removal of existing bridge deck elements, sidewalk blocks, and monolithic concrete pavement in spans 1–7;
construction of prefabricated-monolithic supports in spans 7–11 on existing foundations;
installation of I-shaped pre-stressed girders for spans 7–11;
construction of a monolithic reinforced concrete slab for the roadway and sidewalks;
installation of rolled waterproofing;
installation of closed-type expansion joints;
application of asphalt concrete pavement;
installation of drainage and water disposal systems for the roadway;
installation of galvanized pedestrian and barrier railings;
construction of connection elements between the bridge and approaches;
repair and anti-corrosion protection of concrete surfaces on supports and span structures;
anti-corrosion protection of metal surfaces on existing span structures.
project status
Completed.
project description
Major repair of the bridge over the Bilous river on the state road Chernihiv — Lyubech, Chernihiv region.
Consequence class (responsibility level): CC2 – medium consequences.
Completion timeframe: 2023.
General specifications:
Road category: III;
Bridge length: 48.80 m;
Span structure layout: 15 + 18 + 15 m;
Number of traffic lanes: 2;
Bridge width: 10.54 m;
Dimensions: 8.0 + 2×0.75 m;
Temporary loads: A-11, NK-80.
Scope of work:
Dismantling of damaged structures of the existing bridge;
Construction of monolithic foundations for supports on driven reinforced concrete piles;
Installation of prefabricated-monolithic supports;
Assembly of I-shaped pre-stressed girders for span structures;
Construction of a monolithic reinforced concrete slab for the roadway and sidewalks;
Installation of spray-applied waterproofing;
Installation of closed-type expansion joints;
Application of asphalt concrete pavement;
Installation of drainage and water disposal systems;
Installation of galvanized pedestrian and barrier railings;
Construction of connection elements between the bridge and approaches;
Anti-corrosion protection of steel and concrete surfaces of supports and span structures.
project status
Completed.
project description
Consequence class (responsibility level): CC2 – medium consequences.
Completion timeframe: 2023.
General specifications:
Bridge length: 108.95 m;
Span structure layout: 6×18 m;
Number of traffic lanes: 2;
Bridge width: 10.84 m;
Dimensions: 8.3 + 2×1.0 m;
Temporary loads: H-30, NK-80.
Scope of work:
Dismantling of existing bridge structures (asphalt concrete pavement, sidewalk blocks, monolithic slab, railing barriers, transition slabs, and abutment walls);
Construction of a monolithic reinforced concrete slab for the span structure;
Installation of closed-type expansion joints;
Application of spray-applied waterproofing;
Construction of connection elements between the bridge and approaches;
Installation of pavement on the bridge and approaches;
Anti-corrosion protection of steel and concrete surfaces of supports and span structures.
project status
Completed.
project description
project status
project description
project status
project description
Reconstruction of the bridge over the Tagamlyk river, Mashivka.
Existing bridge: The bridge was built in 1972. It is designed for loads of N-30, NK-80. According to the survey report developed by the State Enterprise "DerzhdorNDI" in June 2019, the bridge is in operational condition 5 — inoperable.
Bridge length — 43.6 m.
The structure is in condition 5 — inoperable.
Bridge after reconstruction:
The project provides for the implementation of a complex of construction works to improve the operational condition of the bridge and approaches, bring the geometric characteristics of the bridge and approaches to the requirements of current regulatory documents. It is also planned to bring the load-bearing capacity of the bridge to the requirements of current regulatory documents, namely, the passage of temporary loads of A-11 and NK-80 on the bridge, as for a motor road of the IV technical category.
The reconstruction project provides for:
arrangement of a temporary bypass;
dismantling of the existing bridge deck structure;
dismantling of existing reinforced concrete beams (slabs) of the span structure;
dismantling of existing reinforced concrete crossbars of bridge supports;
testing of bridge support piles;
repair of support posts;
installation of new reinforced concrete crossbars and trusses of bridge supports;
installation of cabinet walls on the bank supports of the bridge;
installation of rubber support parts 250x200x32;
manufacture and installation of new reinforced concrete beams of the span structure 1 m high;
installation of modern hermetic deformation joints;
installation of a monolithic reinforced concrete slab of the carriageway;
installation of a bridge connection with the embankment using reinforced concrete transition slabs;
installation of waterproofing of the carriageway slab and transition slabs;
installation of drainage;
project status
Completed.
project description
Reconstruction of the bridge over the Psel river, Hadyach.
Consequence class (responsibility level): CC3 – significant.
consequences. Works completed in 2019–2020.
General specifications:
Bridge length: 219.04 m;
Width: 7.0 m with two sidewalks of 0.75 m each;
Total span length: 16.76 m;
River crossing angle: 90°.
Scope of work:
replacement of the existing span structure with a new beam span featuring a monolithic slab 0.2 m thick. Seven I-beam girders are installed in each span with a 1.65 m axis spacing.
dismantling of existing beams on all supports, reinforcement of support bodies and foundations with additional piles. Installation of a new beam with dimensions of 0.8×1.69×11.05 m.
project status
Completed.
project description
The pedestrian circle on Les Kurbas Avenue (Borschagivka) in Kyiv city repaired
project status
Work is complete
project description
The pedestrian bridge on the Saperno-Slobidskaya street of Kyiv has been repaired
project status
Work is finished
project description
The pedestrian bridge on the Heroyiv Nebesnoyi Sotni Alley was repaired.
List of works:
Disassembly of the bridge web
Disassembly of lining walls of supports
Repair of supports and retaining walls
Repair and anti-corrosion protection of the structure
Repair and corrosion protection of the railing and lighting supports
Arrangement of a bridge cloth, arrangement of deformation seams
Installation of pipe sewerage, reclamation
project status
Completed.
project description
Overhaul of overpasses at the intersection of Bogatyrskaya Str. and Stepan Bandera avenue (138)
project status
The class of consequences (responsibility) — CC3.
Deadline: 2019—2020.
The works are being carried out (the first stage of the overpass repair from Minsk square).
General data:
The length of the overpass is 167.23 m
Overall width — G 9.6 + sidewalks (1.2 + 0.75 m) angle of intersection of the highway L=41°
Works:
Sublimation of runway beams and replacement of support parts
Arrangement of monolithic slabs and sidewalks
Eliminator waterproofing and deformation joints
Asphalt concrete pavement arrangement
Installation of galvanized metal barrier and barrier
Arrangement of asphalt concrete covering on approaches
Repair and anticorrosive protection of the support elements and the fixed structure
project description
Work is completed to restore the bridge over the river Seversky Donets in Stanitsa Luganska, which was destroyed during hostilities in 2015.
Construction actually lasted less than two months — from September 2 to November 20.
The width of the bridge is 2.5 meters.
Object of national importance.
project status
Completed
To that moment pedestrian traffic is restored.
project description
Services on current repair of the pedestrian bridge at the intersection of Magnitogorskaya Street with Svyatoshyno-Brovary metro line near the Chernihivska metro station
project status
The work was successfully completed in 2019.
Types of work:
Repair of reinforced concrete structures of run structures, supports, stairs, bridge
Repair and reinforcement of the fence
Arranging lullabies on the stairs of the bridge
Arrangement of anticorrosive protection of structures using modern technologies and materials
project description
Overhaul of overpasses at the intersection of Bohatyrska street and Obolonsky Avenue in the Obolon district of Kyiv.
The class of consequences (responsibility) — CC3.
General data:
The length of the overpass — 130.86 m
Overall width G13, 36 + sidewalks (3,3 +0,8 g) road crossing angle L=44° 25`
project status
The period of works: 2019—2020.
Works are carried out (1st stage of repair).
List of works:
Jacking beams spans and replacement of bearing parts
Arrangement of monolithic slabs and sidewalks
Arrangement of waterproofing Eliminator and deformation joints
Arrangement of asphalt pavement.
Installation of galvanized metal railing and barrier fence
Arrangement of asphalt concrete pavement on approaches
Repair and anticorrosive protection of elements of supports and the fed structure
project description
Execution of works on the current (average) repair of the Pedestrian Bridge at the intersection of Borshchagivska Str. and Vadyma Hetmana Str. (Industrialna Str.)
project status
The works were completed in 2019.
Types of work:
Repair of reinforced concrete structures of run structures, supports, stairs, bridge
Repair and reinforcement of the fence
Arranging lullabies on the stairs of the bridge
Arrangement of anticorrosive protection of structures using modern technologies and materials
project description
Performance of works on overhaul of the overpass at the intersection of Komarov and Les Kurbas avenues with the railway Kyiv-Volynsky— Svyatoshino near the platform "Borschagovka".
General data:
The length of the overpass — 167.44 m
Width — 36.16 m
Road Trip — 2 G10, 5+3,0
Tramway G8, 04x2 ways
The class of consequences (responsibility) — CC3 (significant consequences)
project status
Deadline: 2019—2020.
Works are carried out (1st stage of repair).
Works:
Repair and restoration of structural geometry with repair materials and monolithic concrete
Reinforcement of structures with carbon ribbons and cloths
Replacement of precast units beams and the device pottermania
Approaches:
Reconstruction of interface elements (Cabinet wall, openings, transition plates, ladders)
Arrangement of asphalt concrete pavement of the roadway
Arrangement of communication cables and SCB in the tramway plate and reconstruction of tram lighting lines
Device of galvanized metal barrier fence on the side of the tramway
Sidewalks:
Installation of prefabricated elements of paving blocks and the device of monolithic sections
Arrangement of waterproofing Eliminator
Bridgemaster system coverage device
Installation of galvanized metal railing and barrier fence
Reconstruction of lighting lines and cable lines of lighting and cable lines of KL-10 and communication
Other work:
The arrangement of the system ACROSS
Repair of stairs leading to the railway platform
Replacement europavilions
Reconstruction to Consul Stoyanov
Replacement of rail-sleeper grid structures and reconstruction of tram contact network line
Superstructure:
Replacement of the extreme beams of the superstructure along the entire length of the bridge and all the beams in the span A-1 with the installation of individual supporting structures TPK to maintain the existing heating line, placed extreme beams on both sides of the overpass
Repair with restoration of geometry of other beams
Road and Tram travel:
Arrangement of monolithic plate with boxes for tram rails
Arrangement of deformation seams and waterproofing Eliminator
Installation of t-62 tram rails and reconstruction of tram network lines
Protection of the tramway plate by the Bridgemaster system
project description
Repair, strengthening and restoration of the overpass on separate sites through the railway on 345 + 637 km at the current average repair of the public highway of state value M-03 Kyiv—Kharkov—Dovzhansky (to Rostov-na-Donu).
General data:
The length of the overpass — 60.65 m
Width — 14,146 m
project status
Location: Poltava region, Ukraine.
Deadline: 2018.
Works:
Arrangement of monolithic reinforced concrete slab reinforcement and monolithic sidewalks
Installation of bridge waterproofing with Eliminator materials
Construction of asphalt concrete cover
Installation of galvanized metal barrier and railing
Arrangement of deformed seams of closed type
Arranging elements with approaches
Laundry wall arrangement
Repair and anti-corrosion protection of supports and running structures using modern technologies and materials
project description
Services for the current repair of 4 pedestrian bridges at the intersection of Peremogi Avenue with the Kiltseva Doroga in Kyiv
project status
Location: Kyiv.
Work deadline is 2018.
The work was completed in 2018.
Works:
Repair of reinforced concrete structures of girder structures, supports, stairs and stairs
Arrangement of a protective layer, surfacing waterproofing and asphalt concrete coating
Repair and strengthening of the fence
Arrangement of wheelchairs
Anti-corrosion coating using modern technologies and materials
project description
Overhaul of the overpass at the intersection of Elena Teliga and Frunze (Kirillovskaya) in the Podolsk district of Kyiv.
Class consequences (responsibility) SS3 — significant consequences.
General data:
Length — 56.4 m
Width — 28.74 m
project status
The work was completed in 2018.
List of works:
Installation of reinforced concrete reinforced concrete slabs and monolithic sidewalk consoles
Replacement of 2 extreme beams of the running structure
Bridge liner waterproofing (Eliminator system material)
Installation of galvanized metal barrier and railing
Arrangement of deformed seams of closed type
Arrangement of communication elements
Repair and anticorrosive protection of support structures and running structure using modern technologies and materials
project description
Provision of services for the current (average) repair of the trestle exit from the Dniprovsky descent on the Naberezhnye highway near the metro station "Dnipro" in the city of Kyiv
project status
The works are fully completed in 2019.
Types of work:
Repair of runway beams, supports and eaves blocks